People talking in a building under constructionPeople talking in a building under construction

Investment Programme

People talking in a building under construction
Northampton Waterside CampusNorthampton Waterside Campus

Investment Programme

Northampton Waterside Campus
Northampton College Advanced Engineering CentreNorthampton College Advanced Engineering Centre

Investment Programme

Northampton College Advanced Engineering Centre
School students having a discussion with their teacherSchool students having a discussion with their teacher

Investment Programme

School students having a discussion with their teacher
A Starship Robot driving down a streetA Starship Robot driving down a street

Investment Programme

A Starship Robot driving down a street
East Northamptonshire Enterprise CentreEast Northamptonshire Enterprise Centre

Investment Programme

East Northamptonshire Enterprise Centre

Wellingborough Campus Renewal Project

1st October 2018

This project has seen substantial works to the Tresham College tower block in Wellingborough (part of the Bedford College Group), refurbishment of other on-site buildings as well as improvements to the college access.

Funding Stream: Local Growth Fund
LGF Awarded: £7.5million (and £1.2million additional funds)
Total Project Cost: £11.2million
Delivery Partner: Bedford College Group
Project Status: Opened September 2020
Projected Outputs: 1066 additional new learners per annum by 2021/22
Website: https://www.tresham.ac.uk/wellingborough-campus/

Project Evaluation Report

December 2020

The new college campus opened to students on 14 September 2020 and an official opening ceremony will follow in early 2021. The extensive refurbishment has been a fantastic achievement!

Wellingborough Campus December 2020

July 2020

Great progress has been made on site as the campus redevelopment progresses to be ready for a September opening for new students in Wellingborough.

May 2020

These pictures show how Wellingborough's newly refurbished town centre college will look when it opens later this year. All the building work is on schedule ahead of the campus opening to 1,000 students and staff in the Autumn. Read more.

March 2020

Work is on schedule for Wellingborough's newly refurbished town centre college to open in September to 1,000 students and staff.

The long-awaited refit of the tower block, part of a £10 million project, can now be seen and includes the Tresham College signage...Read more.

November 2019

The £10m re-launch of Tresham College’s Wellingborough campus reached a significant milestone on November 27th with the first cladding panel being put in place...Read more.

July 2019

  • Floors have been stripped ready for the new install
  • Mobile control unit lifted off the roof
  • Roof cleared of mast 
  • The new roof has been put on the hall

March 2019

  • Asbestos has been removed from the ceiling 
  • The demolition is on-going 
  • New protected electrical supplies installed to each floor
  • New wireless fire alarm installed to all doors